Alert: Landfill Gas Collection and Control Equipment Unplanned Down Time on 11/16/2026 at 4:30pm; Resumed Operation on 11/16/2026 by 6:36pm
On Monday, November 16, 2026, Chiquita experienced unplanned downtime of Flare 1, Flare 2, Flare 3, Zeeco TOx #1, Zeeco TOx #2, Zeeco TOx #6, Zeeco TOx #7, and Parnell TOx at approximately 4:30pm, due to a shutdown of site power. Later that day, Flares 1 and 3 resumed operation at approximately 6:04pm, Zeeco TOx #1 at approximately 6:34pm, Zeeco TOx #2 at approximately 6:20pm, and Zeeco TOx #6 at approximately 6:26pm. Parnell TOx resumed operation at approximately 6:46pm but experienced additional unplanned downtime due to flame failure on Tuesday, November 17, 2026, at approximately 1:10am. Parnell Tox resumed operation at approximately 2:18am. Flare 2 resumed operation on Tuesday, November 17, 2026 at approximately 2:44am but experienced additional unplanned downtime due to flame failure at approximately 5:32am. Flare 2 and Zeeco TOx #7 remain offline as of 9:00am on Tuesday, November 17, 2026. The downtime of Flare 2 is anticipated to last for up to 3 hours and 58 minutes, and the downtime of Zeeco TOx #7 is anticipated to last for up to 17 hours and 31 minutes.
Due to this downtime, there may be a possibility of increased odors in the community during the indicated time period.
Under Condition 81 of the Modified Stipulated Order for Abatement in Case No. 6177-4, Chiquita Canyon, LLC (Chiquita) is required to notify the community (i) if any individual control device has downtime which is anticipated to last 30 minutes or more or once any downtime for an individual control device reaches 30 minutes of downtime or (ii) if the downtime of any combination of landfill gas collection equipment results or is planned to result in a reduction of gas flow to control devices by 10% or more and the downtime is anticipated to last 30 minutes or more or once any downtime for such devices reach 30 minutes of downtime. Pursuant to Condition 81, Chiquita is also required to notify the community once the gas collection and control equipment has resumed operation.
Chiquita continues to work to diligently comply with regulator orders.