Stipulated Order for Abatement
This page was last updated on January 17, 2025
Summary of Activities
Chiquita’s December 2024 State of the Landfill Report is available here (en Español). This report provides a summary overview of the Elevated Temperature Landfill event that is occurring in a portion of the Landfill and the efforts Chiquita and its experts are taking to mitigate this event. This report includes data and information as of October 31, 2024 or Quarter Three of 2024. Chiquita intends to update this report periodically with more recent data, information, and analysis.
Here is a summary of the activities Chiquita has taken and/or mitigation measures Chiquita has implemented over the past week (1/13/25 – 1/17/25).
The source of any odors coming from the Chiquita Canyon Landfill is an increase in the production of landfill gas (LFG) and liquids at the Landfill. This increase in LFG and liquids production is due to an abnormal biotic or abiotic process (also known as a landfill reaction) taking place deep within a lined, but older and, inactive portion of the Landfill waste mass. This reaction is not a fire or subsurface oxidation event within the waste mass, and is not related to current waste disposal operations at the Landfill.
Chiquita continues to work diligently with all of its regulators to address this landfill reaction and any related impacts. In November 2023, local, state, and federal agencies formed a Multi-Agency Critical Action Team (“MCAT”), led by the U.S. Environmental Protection Agency (“EPA”), to coordinate regulatory efforts. In March 2024, this coordination shifted into a new phase, and the County, CalEPA, and U.S. EPA created a Response Multi-Agency Coordination Group (“R-MAC”) composed of federal, state, and local onsite coordinators. On October 14, 2024, the RMAC ended the emergency response phase of their work and the R-MAC disbanded. The MCAT now leads the regulatory efforts at the Landfill.
Public Notification: Toe Drain Installation Work
Chiquita has installed a new toe drain at the west and north slopes of the landfill as part of its continued mitigation of the ongoing elevated landfill temperature (ETLF) event or reaction. The west and north slopes were impacted by the increased leachate production. To avoid odors from the leachate, as well as to prevent leachate from commingling with stormwater, the west slope was previously covered by a plastic cover called a scrim. To improve leachate drainage and conditions at the west and north slopes, Chiquita removed the scrim and excavated into the waste mass to install a drain and sumps that will better control the leachate. Chiquita has now completed the excavation portion of this project, and has installed the new toe drain and covered the top deck, north slope, and west slope areas with a 30-mil geosynthetic cover.
Because no further excavation is expected to be performed as part of this project, Chiquita is discontinuing its weekly updates on this project. Chiquita will continue to work with its regulators to address the reaction and any impacts.
Odor Mitigation Efforts
In coordination with its many regulators, Chiquita is doing everything in its power to reduce odors originating from the Landfill. On September 6, 2023, Chiquita entered into a Stipulated Order for Abatement with the South Coast AQMD (view the Spanish version) that requires Chiquita to implement many mitigation measures designed to study the reaction, its potential impacts, and potential ways to mitigate the reaction and its potential impacts. This Stipulated Order has since been modified on January 17, 2024, March 21, 2024, April 24, 2024, August 27, 2024 and November 13, 2024. The November 13, 2024 Modified Stipulated Order will be posted once available.
On February 21, 2024, Chiquita received a UAO from the EPA requiring Chiquita to submit workplans for its existing and future efforts to address the reaction and any impacts and conduct additional work to address the reaction.
On June 6, 2024, Chiquita received a Compliance Order from the LEA requiring Chiquita to implement additional mitigation measures to address the reaction.
Among other things, in accordance with the Stipulated Order, the LEA’s letters, and the UAO, Chiquita is implementing the following mitigation measures:
Completed actions
- Submitted an updated liquid modeling report
- Installed a remote monitoring system for temperature in 20 wellheads
- Submitted a source test report for leachate and condensate vapor sampling at the Landfill
- Submitted the Winder Barrier Evaluation Study
- Submitted Ambient Air and Emissions Monitoring Study
- Submitted Health Impacts and Odor Impacts Assessment Reports to South Coast AQMD
- Installed flow meters on the landfill gas piping
- Completed two quarterly inspections of the landfill gas and liquids piping network
- Installed pressure gauges on the leachate tanks
- Submitted an expert report on landfill gas generation and control capacity
- Submitted Model of Liquid Generation and Total Quantity Report to South Coast AQMD
- Submitted Pipe Materials Temperature Study to South Coast AQMD
- Submitted further revised dewatering guidelines to South Coast AQMD
- Submitted the findings of the second flux chamber study to South Coast AQMD
- Submitted permit applications to incorporate the leachate treatment system into Chiquita’s existing landfill gas control system
- Submitted a permit application for the landfill gas collection system under the geosynthetic cover
- Installed 117 dewatering pumps in landfill gas wells
- Submitted a revised proposal for additional air modeling
- Installed 20 temperature monitoring probes in and around the reaction area
- Submitted a report on potential DMS treatment methods
- Submitted reports on the testing of the headspace vapors from the leachate tanks
- Submitted a work plan to restart dewatering
- Submitted a recommendation on the installation of a remote well pressure and temperature monitoring system
- Submitted permit applications to further modify Chiquita’s landfill gas and liquids collection systems
- Designated an Inspection Liaison
- Submitted workplans listing the actions Chiquita is taking and plans to take to address the reaction
- Submitted a report on the feasibility of containment of discharges of pressurized leachate
- Submitted a slope stability analysis of the western and northern slopes of the Reaction Area
- Installed and began operating a new permanent flare (Flare 3)
- Installed and began operating a second portable thermal oxidizer
- Installed over 260 new vertical wells
- Submitted design and installation schedules for the continued expansion of the landfill gas wellfield
- Submitted an application for a Rule 1150 excavation management plan
- Submitted an updated workplan and installation schedule for the geosynthetic cover
- Submitted the proposal for an additional air modeling study to South Coast AQMD
- Submitted a slope stability analysis work plan to the LEA
- Submitted the protocol for an additional flux chamber study to South Coast AQMD
- Submitted a report on the cause(s) of the landfill reaction and solutions to slow and stop the reaction to South Coast AQMD
- Submitted initial and revised dewatering guidelines to South Coast AQMD
- Submitted a report on air dispersion modeling and a study to determine odor and emission transport of odors from the Landfill to South Coast AQMD
- Submitted a report on the feasibility and availability of a continuous community emission monitoring system for DMS to South Coast AQMD
- Submitted a report on landfill best management practices and alternative methods to minimize the release of fugitive surface gas and related odors to South Coast AQMD
- Submitted the findings of the initial flux chamber study to South Coast AQMD
- Submitted an application for a fourth permanent flare
Ongoing actions
- Report on leachate tank numbers and quantities of liquid collected and treated on a weekly basis
- Increase 24-hour sampling for VOCs in the community
- Host biweekly and monthly meetings between technical teams at Chiquita and South Coast AQMD
- Expeditiously dewater the landfill to the maximum extent feasible
- Implement mitigation measures while drilling new wells
- Prevent standing leachate and the pooling or ponding of leachate exposed to the atmosphere
- Conduct twice daily inspections for liquid/leachate seepage, once in the morning and once in the afternoon
- Install well boots seals on all wells in the Reaction Area
- Install temperature monitoring devices in and around the Reaction Area
- Measure and record landfill gas and leachate temperatures
- Measure and record quantities of leachate sent offsite for disposal/treatment
- Measure, sample, and analyze leachate monthly
- Conduct daily inspections of the landfill cover and geosynthetic cover, and repair identified issues
- Conduct odor surveillance twice each operating day, once in the morning and once at night
- Sample and analyze the sulfur compounds in the landfill gas daily
- Conduct surface sampling across the Reaction Area every two weeks
- Submit monthly reports to the South Coast AQMD containing information and data collected under the Stipulated Order as well as updates on the implementation of the longer-term improvement projects to the landfill gas and liquids collection and control systems, landfill cover, and more
- Expand the landfill gas and liquids collection and control systems
- Procure and install a geosynthetic cover over western and northern portions and the top deck of the Reaction Area
- Maintain a variety of odor control systems around the Landfill
Odor and Maintenance Logs
Monthly reports submitted to the South Coast AQMD on the 20th of every month as required by Condition 8 of the Stipulated Order for Abatement:
- November 2024 (en Español)
- October 2024 (en Español)
- September 2024 (en Español)
- August 2024 (en Español)
- July 2024 (en Español)
- June 2024 (en Español)
- May 2024 (en Español)
- April 2024
- March 2024 (en Español)
- February 2024 (en Español)
- January 2024 (en Español)
- December 2023 (en Español)
- November 2023 (en Español)
- October 2023 (en Español)
- September 2023 (en Español)
- August 2023 (en Español)
Chiquita’s weekly well drilling updates required by Condition 15(c) to South Coast AQMD:
- January 10, 2025
- January 3, 2025
- December 27, 2024 (en Español)
- December 20, 2024 (en Español)
- December 13, 2024 (en Español)
- December 6, 2024 (en Español)
- November 27, 2024 (en Español)
- November 22, 2024 (en Español)
- November 15, 2024 (en Español)
- November 8, 2024
- November 1, 2024 (en Español)
- October 25, 2024 (en Español)
- October 18, 2024 (en Español)
- October 11, 2024 (en Español)
- October 7, 2024 (en Español)
- September 30, 2024 (en Español)
- September 23, 2024 (en Español)
- September 16, 2024 (en Español)
- September 9, 2024 (en Español)
- September 2, 2024
- August 26, 2024 (en Español)
- August 19, 2024 (en Español)
- August 12, 2024 (en Español)
- August 5, 2024 (en Español)
- July 29, 2024 (en Español)
- July 22, 2024 (en Español)
- July 15, 2024 (en Español)
- July 8, 2024 (en Español)
- July 1, 2024 (en Español)
- June 24, 2024 (en Español)
- June 17, 2024 (en Español)
- June 10, 2024
- June 3, 2024 (en Español)
- May 27, 2024 (en Español)
- May 20, 2024
- May 13, 2024 (en Español)
- May 6, 2024 (en Español)
- April 29, 2024 (en Español)
- April 22, 2024 (en Español)
- April 15, 2024 (en Español)
- April 8, 2024 (en Español)
- April 1, 2024 (en Español)
- March 25, 2024 (en Español)
- March 18, 2024 (en Español)
- March 11, 2024
- March 4, 2024
- February 26, 2024 (en Español)
- February 19, 2024 (en Español)
- February 12, 2024 (en Español)
- February 5, 2024 (en Español)
- January 29, 2024 (en Español)
- January 22, 2024 (en Español)
Chiquita’s weekly leachate inspection reports prepared pursuant to Condition 27(c) to South Coast AQMD:
- January 14, 2025
- January 7, 2025
- December 31, 2024 (en Español)
- December 24, 2024 (en Español)
- December 17, 2024 (en Español)
- December 10, 2024 (en Español)
- December 3, 2024 (en Español)
- November 26, 2024 (en Español)
- November 19, 2024 (en Español)
- November 12, 2024
- November 5, 2024 (en Español)
- October 29, 2024 (en Español)
- October 22, 2024 (en Español)
- October 15, 2024 (en Español)
- October 8, 2024 (en Español)
- October 1, 2024 (en Español)
- September 24, 2024 (en Español)
- September 17, 2024 (en Español)
- September 10, 2024 (en Español)
- September 3, 2024
- August 27, 2024 (en Español)
- August 20, 2024 (en Español)
- August 13, 2024 (en Español)
- August 6, 2024 (en Español)
- July 30, 2024 (en Español)
- July 23, 2024 (en Español)
- July 16, 2024 (en Español)
- July 9, 2024 (en Español)
- July 2, 2024 (en Español)
- June 25, 2024 (en Español)
- June 18, 2024 (en Español)
- June 11, 2024
- June 4, 2024 (en Español)
- May 28, 2024 (en Español)
- May 21, 2024
- May 14, 2024 (en Español)
- May 7, 2024 (en Español)
- April 30, 2024 (en Español)
- April 23, 2024 (en Español)
- April 16, 2024 (en Español)
- April 9, 2024 (en Español)
- April 2, 2024 (en Español)
- March 26, 2024 (en Español)
- March 19, 2024 (en Español)
- March 12, 2024
- March 5, 2024
- February 27, 2024 (en Español)
- February 20, 2024 (en Español)
- February 13, 2024 (en Español)
- February 6, 2024 (en Español)
- January 30, 2024 (en Español)
- January 23, 2024 (en Español)
Chiquita’s reports to South Coast AQMD under Condition 27(e) summarizing leachate leak and spill information:
- January 7, 2025
- January 7, 2025
- December 29, 2024 (en Español)
- December 27, 2024 (en Español)
- December 24, 2024 (en Español)
- December 21, 2024 (en Español)
- December 12, 2024 (en Español)
- November 27, 2024 (en Español)
- November 27, 2024 (en Español)
- November 12, 2024
- November 7, 2024 (en Español)
- November 4, 2024 (en Español)
- November 1, 2024 (en Español)
- October 31, 2024 (en Español)
- October 26, 2024 (en Español)
- October 25, 2024 (en Español)
- October 25, 2024 (en Español)
- October 25, 2024 (en Español)
- October 24, 2024 (en Español)
- October 23, 2024 (en Español)
- October 20, 2024 (en Español)
- October 18, 2024 (en Español)
- October 18, 2024 (en Español)
- October 15, 2024 (en Español)
- October 11, 2024 (en Español)
- October 2, 2024 (en Español)
- September 22, 2024 (en Español)
- September 17, 2024 (en Español)
- September 10, 2024 (en Español)
- September 9, 2024 (en Español)
- September 7, 2024 (en Español)
- September 7, 2024 (en Español)
Chiquita’s reports to South Coast AQMD summarizing laboratory results collected under Condition 42(x):
- December 24, 2024 (en Español)
- December 21, 2024 (en Español)
- December 20, 2024 (en Español)
- December 19, 2024 (en Español)
- December 18, 2024 (en Español)
- November 21, 2024 (en Español)
- November 20, 2024 (en Español)
- November 10, 2024
- November 9, 2024
- November 8, 2024
- November 7, 2024 (en Español)
- November 6, 2024 (en Español)
- November 3, 2024 (en Español)
- November 2, 2024 (en Español)
- November 1, 2024 (en Español)
- October 31, 2024 (en Español)
- October 30, 2024 (en Español)
- October 27, 2024 (en Español)
- October 26, 2024 (en Español)
- October 25, 2024 (en Español)
- October 24, 2024 (en Español)
- October 23, 2024 (en Español)
- October 20, 2024 (en Español)
- October 19, 2024 (en Español)
- October 18, 2024 (en Español)
- October 18, 2024 (en Español)
- October 17, 2024 (en Español)
- October 13, 2024 (en Español)
- October 11, 2024 (en Español)
- October 10, 2024 (en Español)
- October 9, 2024 (en Español)
- October 7, 2024 (en Español)
- October 4, 2024 (en Español)
- October 3, 2024 (en Español)
- October 2, 2024 (en Español)
- September 29, 2024
- September 28, 2024 (en Español)
- September 25, 2024 (en Español)
- September 23, 2024 (en Español)
- September 22, 2024 (en Español)
- September 19, 2024 (en Español)
- September 16, 2024 (en Español)
- September 10, 2024 (en Español)
- September 9, 2024 (en Español)
- September 5, 2024 (en Español)
- September 3, 2024 (en Español)
- August 30, 2024 (en Español)
Chiquita’s weekly report to South Coast AQMD under Condition 65 summarizing leachate pump installation activities:
- January 10, 2025
- January 3, 2025
- December 27, 2024 (en Español)
- December 20, 2024 (en Español)
- December 13, 2024 (en Español)
- December 6, 2024 (en Español)
- November 27, 2024 (en Español)
- November 22, 2024 (en Español)
- November 15, 2024 (en Español)
- November 8, 2024
- November 1, 2024 (en Español)
- October 25, 2024 (en Español)
- October 18, 2024 (en Español)
- October 11, 2024 (en Español)
- October 4, 2024 (en Español)
- September 27, 2024 (en Español)
- September 20, 2024 (en Español)
- September 13, 2024 (en Español)
- September 6, 2024 (en Español)
- August 30, 2024
- August 23, 2024 (en Español)
- August 16, 2024 (en Español)
- August 9, 2024 (en Español)
- August 2, 2024 (en Español)
- July 26, 2024 (en Español)
- July 19, 2024 (en Español)
- July 12, 2024 (en Español)
- July 5, 2024 (en Español)
- June 28, 2024 (en Español)
- June 21, 2024 (en Español)
- June 14, 2024 (en Español)
- June 7, 2024
- May 31, 2024 (en Español)
- May 24, 2024 (en Español)
- May 17, 2024
- May 10, 2024 (en Español)
- May 3, 2024 (en Español)
- April 26, 2024 (en Español)
- April 19, 2024 (en Español)
- April 12, 2024 (en Español)
- April 5, 2024 (en Español)
- March 29, 2024 (en Español)
Chiquita’s weekly report to South Coast AQMD under Condition 53 on leachate tank numbers and quantities of leachate collected:
- January 15, 2025
- January 8, 2025
- December 31, 2024 (en Español)
- December 24, 2024 (en Español)
- December 18, 2024 (en Español)
- December 11, 2024 (en Español)
- November 25, 2024 (en Español)
- November 18, 2024 (en Español)
- November 11, 2024 (en Español)
- November 4, 2024
- October 28, 2024 (en Español)
- October 21, 2024 (en Español)
- October 14, 2024 (en Español)
- October 7, 2024 (en Español)
- September 30, 2024 (en Español)
- September 23, 2024 (en Español)
- September 16, 2024 (en Español)
- September 9, 2024 (en Español)
- September 2, 2024 (en Español)
- August 26, 2024
- August 19, 2024 (en Español)
- August 12, 2024 (en Español)
- August 5, 2024 (en Español)
- July 29, 2024 (en Español)
- July 22, 2024 (en Español)
- July 15, 2024 (en Español)
- July 8, 2024 (en Español)
- July 1, 2024 (en Español)
- June 24, 2024 (en Español)
- June 17, 2024 (en Español)
- June 10, 2024 (en Español)
- June 3, 2024
- May 27, 2024 (en Español)
- May 20, 2024 (en Español)
- May 13, 2024
- May 6, 2024 (en Español)
- April 29, 2024 (en Español)
- April 22, 2024 (en Español)
- April 15, 2024 (en Español)
- April 8, 2024 (en Español)
- April 1, 2024 (en Español)
- March 25, 2024 (en Español)
Chiquita’s follow-up written reports to South Coast AQMD under Condition 82 regarding planned and unplanned downtime of LFG collection and control equipment:
- January 15, 2025
- January 14, 2025
- January 10, 2025
- January 10, 2025
- January 9, 2025
- December 25, 2024 (en Español)
- December 23, 2024 (en Español)
- December 15, 2024 (en Español)
- December 15, 2024 (en Español)
- December 15, 2024 (en Español)
- December 13, 2024 (en Español)
- December 13, 2024 (en Español)
- December 12, 2024 (en Español)
- December 9, 2024 (en Español)
- December 8, 2024 (en Español)
- December 8, 2024 (en Español)
- December 6, 2024 (en Español)
- December 6, 2024 (en Español)
- December 6, 2024 (en Español)
- December 4, 2024 (en Español)
- December 4, 2024 (en Español)
- December 2, 2024 (en Español)
- December 2, 2024 (en Español)
- November 29, 2024 (en Español)
- November 27, 2024 (en Español)
- November 27, 2024 (en Español)
- November 27, 2024 (en Español)
- November 26, 2024 (en Español)
- November 26, 2024 (en Español)
- November 25, 2024 (en Español)
- November 25, 2024 (en Español)
- November 24, 2024 (en Español)
- November 24, 2024 (en Español)
- November 18, 2024 (en Español)
- November 16, 2024 (en Español)
- November 16, 2024 (en Español)
- November 13, 2024
- November 12, 2024
- November 11, 2024
- November 8, 2024
- November 6, 2024 (en Español)
- November 4, 2024
- November 4, 2024
- November 4, 2024 (en Español)
- October 30, 2024 (en Español)
- October 30, 2024 (en Español)
- October 27, 2024 (en Español)
- October 26, 2024 (en Español)
- October 26, 2024 (en Español)
- October 26, 2024 (en Español)
- October 25, 2024 (en Español)
- October 25, 2024 (en Español)
- October 24, 2024 (en Español)
- October 23, 2024 (en Español)
- October 23, 2024 (en Español)
- October 22, 2024 (en Español)
- October 14, 2024 (Unplanned) (en Español)
- October 14, 2024 (Planned) (en Español)
- October 12, 2024 (en Español)
- October 9, 2024 (en Español)
- October 7, 2024 (en Español)
- October 6, 2024 (en Español)
- September 30, 2024 (en Español)
- September 27, 2024 (en Español)
- September 26, 2024 (en Español)
- September 25, 2024 (en Español)
- September 24, 2024 (en Español)
- September 21, 2024 (en Español)
- September 19, 2024 (en Español)
- September 18, 2024 (en Español)
- September 16, 2024 (en Español)
- September 12, 2024 (en Español)
- September 11, 2024 (en Español)
- September 8, 2024 (en Español)
- September 7, 2024 (en Español)
- September 5, 2024
- September 5, 2024
- September 4, 2024
- September 4, 2024
- September 3, 2024
- September 2, 2024
View Chiquita’s weekly reports to South Coast AQMD detailing west slope toe drain installation and north slope toe termination activities as required by Condition 85(c):
- January 13, 2025
- January 7, 2025
- December 30, 2024 (en Español)
- December 23, 2024 (en Español)
- December 16, 2024 (en Español)
- December 9, 2024 (en Español)
- November 27, 2024 (en Español)
- November 27, 2024 (en Español)
- November 22, 2024 (en Español)
- November 15, 2024 (en Español)
- November 15, 2024 (en Español)
- November 12, 2024
- November 5, 2024 (en Español)
- October 28, 2024 (en Español)
- October 21, 2024 (en Español)
- October 15, 2024 (en Español)
- October 8, 2024
- October 3, 2024 (en Español)
- September 23, 2024 (en Español)
- September 16, 2024 (en Español)
- September 10, 2024 (en Español)
- September 3, 2024
Reports, Permits, and Other Documents
View the current version of the following documents.
- Safety Data Sheets for the odor neutralizer used at the landfill (en Español).
- Liquid odor neutralizer is mixed with water at a dilution ratio of 1:1200.
- Safety Data Sheet for the Semi-Permanent Vapor Odor Control system (en Español)
- Emergency Response Plan for Chiquita Canyon Landfill (en Español).
- current version of the Landfill’s Conditional Use Permit
- current version of the Landfill’s Storm Water Pollution Prevention Plan
- current version of the Landfill’s Waste Discharge Requirements
- Landfill’s Stipulated Order for Abatement - The November 13, 2024 Modified Stipulated Order will be posted once available.
- EPA’s Unilateral Administrative Order
- LEA’s Compliance Order
South Coast AQMD
Summaries of the monthly Reaction Committee meetings prepared pursuant to Condition 12(f)(iv) of the Stipulated Order:
- Meeting Summary of the December 18, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary of the November 20, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary of the October 23, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary of the September 26, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary of the August 27, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary of the July 24, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary of the June 26, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary from the May 29, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary from the April 16, 2024 Reaction Committee Meeting (en Español)
- Meeting Summary from the March 26, 2024 Reaction Committee Meeting (en Español)
Reaction Area review reports created by the Reaction Committee pursuant to the Stipulated Order:
- December 2024 report
- November 2024 report (en Español)
- October 2024 report (en Español)
- September 2024 report (en Español)
- August 2024 report (en Español)
- July 2024 report (en Español)
- June 2024 report (en Español)
- May 2024 report
- April 2024 report (en Español)
- March 2024 report (en Español)
- February 2024 report
- January 2024 report (en Español)
- December 2023 report (en Español)
- November 2023 report (en Español)
- October 2023 report (en Español)
- September 2023 report (en Español)
Reports created by the Reaction Committee pursuant to the Stipulated Order:
- January 15, 2025 Flux Chamber Study Findings
- January 7, 2025 Model of Liquid Generation and Total Quantity Report
- December 13, 2024 Recommendation on Additional Vapor Flow Testing pursuant to Condition 72(c) (en Español)
- November 15, 2024 Evaluation of Windbreaks and Wind Flow Disruptors Study (en Español)
- September 2, 2024 Ambient Air and Emissions Monitoring Study
- Public Summary of the Health Impacts and Odor Impacts Assessment Reports (en Español)
- August 1, 2024 CTEH Health Impacts Report (en Español)
- Intertox Odor Impacts Assessment Report (en Español)
- July 25, 2024 Revised Landfill Gas Generation and Control Capacity report (en Español)
- July 12, 2024 Revised Landfill Gas Generation and Control Capacity report (en Español)
- June 28, 2024 Landfill Gas Generation and Control Capacity report (en Español)
- June 25, 2024 Model of Liquid Generation and Total Quantity Report (en Español)
- June 21, 2024 Pipe Materials Temperature Study (en Español)
- June 7, 2024 Revised Dewatering Guidelines
- June 3, 2024 Flux Chamber Study Findings (en Español)
- May 16, 2024 Revised Proposal for Additional Air Modeling Study pursuant to Condition 32(b) ( en Español)
- May 8, 2024 Revised Proposal for Additional Air Modeling Study pursuant to Condition 32(b) (en Español)
- April 30, 2024 DMS Treatment Study (en Español)
- April 19, 2024 LFG Wellfield Automated Remote Monitoring Plan (en Español)
- April 4, 2024 Revised Dewatering Guidelines (en Español)
- March 12, 2024 Discharge of Pressurized Leachate Containment Feasibility Study
- February 15, 2024 determination on the use of a portable thermal oxidizer
- January 15, 2024 Health Risks Associated with Exposure to DMS Report (en Español)
- January 15, 2024 Proposal for Additional Air Modeling Study (en Español)
- December 29, 2023 Protocol for Additional Flux Chamber Study
- December 8, 2023 Elevated Temperature Landfill Causation Investigation Report (en Español)
- December 5, 2023 Dewatering Guidelines (en Español)
- December 1, 2023 Ambient Air and Emissions Monitoring Study (en Español)
- December 1, 2023 DMS Continuous Monitoring Feasibility and Availability Report (en Español)
- November 6, 2023 Report on Landfill Best Management Practices (en Español)
- October 31, 2023 Flux Chamber Study Findings (en Español)
Monthly leachate sampling results submitted pursuant to Condition 38 of the Stipulated Order:
- January 2025 results
- December 2024 results (en Español)
- November 2024 results
- October 2024 results (en Español)
- September 2024 results (en Español)
- August 2024 results (en Español)
- July 2024 results (en Español)
- June 2024 results
- May 2024 results (en Español)
- April 2024 results (en Español)
- March 2024 results (en Español)
- February 2024 results (en Español)
- January 2024 results
Other submittals:
- View Chiquita’s January 15, 2025 response to South Coast AQMD’s request for additional information regarding the landfill gas collection system header and conveyance infrastructure
- View Chiquita's December 23, 2024 response to South Coast AQMD’s December 10, 2024 request for additional information regarding the leachate collection system (en Español)
- View Chiquita's December 20, 2024 response to South Coast AQMD's December 12, 2024 Notice to Comply (en Español)
- View Chiquita's November 26, 2024 follow-up response to South Coast AQMD's onsite inspection (en Español)
- View Chiquita's November 15, 2024 source report for leachate and condensate vapor sampling at the landfill (en Español)
- View Chiquita's November 12, 2024 response to South Coast AQMD request for additional information regarding the October 11, 2024 Notice to Comply
- View Chiquita's November 1, 2024 submission to South Coast AQMD providing schematics of the leachate treatment equipment and location of associated sampling ports pursuant to Condition 86(c) (en Español)
- View Chiquita's October 31, 2024 response to South Coast AQMD request for additional information regarding the October 29, 2024 weekly leachate inspection report prepared pursuant to Condition 27(c) (en Español)
- View Chiquita's October 30, 2024 letter to South Coast AQMD regarding findings and solutions on the remote monitoring system required by Condition 66(a)(iv) (en Español)
- View Chiquita's October 29, 2024 response to South Coast AQMD's request for information regarding the October 18, 2024 leak check exceedance event (en Español)
- View Chiquita's October 18, 2024 response to South Coast AQMD's October 11, 2024 Notice to Comply (en Español)
- View Chiquita's October 18, 2024 response to South Coast AQMD's request for additional information regarding the Zeeco thermal oxidizer (en Español)
- View Chiquita's October 15, 2024 letter to South Coast AQMD containing the remote monitoring system information required by Condition 66 (en Español)
- View Chiquita's new and revised Standard Operating Procedures for leachate transfers by pump, leachate transfers by truck, and tank inspections submitted October 14, 2024 pursuant to Condition 27 (f) (en Español)
- View Chiquita’s October 11, 2024 response to Condition 66(a)(iii) (en Español)
- View Chiquita's Standard Operating Procedures for leachate tank operations submitted September 23, 2024 pursuant to Condition 24 (f) (en Español)
- View Chiquita's September 17, 2024 letter to South Coast AQMD containing the remote monitoring system information required by Condition 66 (en Español)
- Chiquita’s August 9, 2024 response to South Coast AQMD’s request for additional information regard the Zeeco thermal oxidizer generator applications (en Español)
- July 30, 2024 response to South Coast AQMD's July 19, 2024 request for additional information regarding the hazardous liquid treatment systems permit (en Español)
- July 25, 2024 response to South Coast AQMD’s July 19, 2024 request for additional information regarding the Landfill Gas Generation and Control Capacity Report
- July 12, 2024 response to South Coast AQMD's June 28, 2024 request for additional information regarding the Zeeco thermal oxidizer (en Español)
- Chiquita's July 11, 2024 response to South Coast AQMD's July 2, 2024 request for additional information regarding the flares (en Español)
- July 3, 2024 response to South Coast AQMD’s June 12, 2024 inspection regarding areas of discoloration in the geosynthetic cover (en Español)
- June 12, 2024 Condition 68 extension request (en Español)
- June 3, 2024 response to SCAQMD’s follow-up questions on the May 7, 2024 Condition 27(c) inspection logs (en Español)
- May 31, 2024 updated waste-in-place map as requested by SCAQMD (en Español)
- May 29, 2024 response to SCAQMD’s request for additional information regarding the May 21 internal combustion engine inventory submitted pursuant to Condition 73 (en Español)
- May 21, 2024 Internal Combustion Engines Greater than 50 Horsepower Inventory pursuant to Condition 73.
- April 29, 2024 MicroGC Workplan pursuant to Condition 36 (en Español)
- April 24, 2024 Leachate Tank Headspace Vapor Sampling report prepared pursuant to Condition 56 (en Español)
- schematic of the leachate treatment/storage system submitted on April 22, 2024 pursuant to Condition 63 (en Español)
- April 18, 2024 Preliminary Leachate Tank Headspace Vapor Sampling report prepared pursuant to Condition 56 (en Español)
- April 18, 2024 updated well design and installation schedule prepared pursuant to Condition 15(b)(i) (en Español)
- 60-day installation update for the continuous volatile organic compound air monitors (en Español)
- leachate sampling results taken pursuant to Condition 37 of the Modified Stipulated Order (en Español)
- Chiquita's workplan to address the landfill reaction prepared pursuant to Condition 50 of the Modified Stipulated Order (en Español)
- March 12, 2024 response to a request for information on updated well information (en Español)
- March 8, 2024 response to a request for additional information on request for higher operating value wells (en Español)
- March 5, 2024 request to drill new landfill gas wells on weekends and legal holidays (en Español)
- February 29, 2024 response to South Coast AQMD’s January 15, 2024 Notice to Comply (en Español)
- February 23, 2024 response to questions re leachate pumps (view the en Español)
- 30-day installation update for the continuous volatile organic compound air monitors (en Español)
- February 9, 2024 response to South Coast AQMD’s January 31, 2024 Notice to Comply (en Español)
- January 31, 2024 wellfield expansion plan pursuant to Condition 15(a) of the Stipulated Order (en Español)
- October 31, 2023 status update on the procurement and installation of the geosynthetic cover pursuant to the Stipulated Order (en Español)
- October 20, 2023 response to South Coast AQMD’s October 6, 2023 Notice to Comply (en Español)
- The reports submitted to the South Coast AQMD under the variance in Case No. 6177-3 are available on the Landfill Reports section of website
Local Enforcement Agency
Weekly updates on cover issues in accordance with Milestone2B:
- Week of January 6, 2025 (with December summary)
- Week of December 30, 2024
- Week of December 23, 2024 (en Español)
- Week of December 16, 2024 (en Español)
- Week of December 9, 2024 (en Español)
- Week of December 2, 2024 (with November summary) (en Español)
- Week of November 25, 2024 (en Español)
- Week of November 18, 2024 (en Español)
- Week of November 11, 2024 (en Español)
- Week of November 4, 2024
- Week of October 28, 2024 (en Español)
- Week of October 21, 2024 (en Español)
- Week of October 14, 2024 (en Español)
- Week of October 7, 2024 (en Español)
- Week of September 30 (with August summary) (en Español)
- Week of September 23, 2024 (en Español)
- Week of September 16, 2024 (en Español)
- Week of September 9, 2024 (en Español)
- Week of September 2, 2024 (en Español)
- Week of August 26, 2024
- Week of August 19, 2024 (en Español)
- Week of August 12, 2024 (en Español)
- Week of August 5, 2024 (with July summary) (en Español)
- Week of July 29, 2024 (en Español)
- Week of July 22, 2024 (en Español)
- Week of July 15, 2024 (en Español)
- Week of July 8, 2024 (en Español)
- Week of July 1, 2024 (with June summary) (en Español)
- Week of June 24, 2024 (en Español)
- Week of June 17, 2024 (en Español)
- Week of June 10, 2024 (en Español)
- Week of June 3, 2024 (with May summary)
- Week of May 27, 2024 (en Español)
- Week of May 20, 2024 (en Español)
- Week of May 13, 2024
- Week of May 6, 2024 (with April summary) (en Español)
- Week of April 29, 2024 (en Español)
- Week of April 22, 2024 (en Español)
- Week of April 15, 2024 (en Español)
- Week of April 8, 2024 (en Español)
- Week of April 1, 2024 (en Español)
- Week of March 25, 2024 (en Español)
- Week of March 18, 2024 (en Español)
- Week of March 11, 2024 (en Español)
- Week of March 4, 2024 (en Español)
- Week of February 26, 2024 (en Español)
- Week of February 19, 2024 (en Español)
- Week of February 12, 2024 (en Español)
- Week of February 5, 2024 (en Español)
- Week of January 29, 2024 (en Español)
- Week of January 22, 2024 (en Español)
- Week of January 15, 2024 (en Español)
- Week of January 8, 2024 (en Español)
- Week of January 1, 2024 (en Español)
Weekly submittals of all temperature monitoring probe data in accordance with Mitigation 1B:
- December 5 – January 15, 2025 update
- November 28 – January 8, 2025 update
- November 21 – January 1, 2025 update (en Español)
- November 14 – December 25, 2024 update (en Español)
- November 7 – December 18, 2024 update (en Español)
- October 31 – December 11, 2024 update (en Español)
- October 24 – December 4, 2024 update (en Español)
- October 17 – November 26, 2024 update (en Español)
- October 10 – November 20, 2024 update (en Español)
- October 3 – November 13, 2024 update
- September 26 – November 6, 2024 update (en Español)
- September 19 – October 30, 2024 update (en Español)
- September 13 – October 23, 2024 update (en Español)
- September 6 – October 17, 2024 update (en Español)
- August 30 – October 10, 2024 update (en Español)
- August 23 – October 3, 2024 update (en Español)
- August 16 – September 26, 2024 update (en Español)
- August 9, 2024 – September 19, 2024 update (en Español)
- August 2, 2024 – September 12, 2024 update (en Español)
- July 26, 2024 – September 5, 2024 update
- July 19, 2024 – August 29, 2024 update (en Español)
- July 12, 2024 – August 22, 2024 update (en Español)
- July 5, 2024 – August 15, 2024 update (en Español)
- June 28, 2024 – August 8, 2024 update (en Español)
- June 21, 2024 – August 1, 2024 update (en Español)
- June 14, 2024 – July 25, 2024 update (en Español)
- June 7, 2024 – July 18, 2024 update (en Español)
- May 31, 2024 – July 11, 2024 update (en Español)
- May 24, 2024 – July 4, 2024 update (en Español)
- May 17, 2024 – June 27, 2024 update (en Español)
- May 10, 2024 – June 20, 2024 update (en Español)
- May 3, 2024 – June 13, 2024 update (en Español)
- April 25, 2024 – June 5, 2024 update (en Español)
- April 25, 2024 – May 29, 2024 update (en Español)
- April 25, 2024 – May 22, 2024 update
- April 25, 2024 – May 15, 2024 update (en Español)
- April 25, 2024 – May 8, 2024 update (en Español)
Updates on the installation of the temperature monitoring probes in accordance with Mitigation Measure #1B. Note that Chiquita stopped submitting these updates once the probes were fully installed. Chiquita now submits weekly submittals of probe data, as shown above:
- May 2, 2024 update (en Español)
- April 25, 2024 update (en Español)
- April 18, 2024 update (en Español)
- April 11, 2024 update (en Español)
- April 4, 2024 update (en Español)
- March 28, 2024 update (en Español)
- March 21, 2024 update (en Español)
- March 14, 2024 update (en Español)
- March 7, 2024 update (en Español)
- February 29, 2024 update (en Español)
- February 22, 2024 update (en Español)
- February 15, 2024 update (en Español)
- February 8, 2024 update (en Español)
- February 1, 2024 update (en Español)
- January 25, 2024 update (en Español)
- January 19, 2024 update (en Español)
- January 11, 2024 update (en Español)
Weekly updates on the installation of the geosynthetic cover in accordance with Milestone 2A. Note that Chiquita stopped submitting these updates once the geosynthetic cover fully installed.
- January 3, 2025 update
- December 27, 2024 update (en Español)
- December 20, 2024 update (en Español)
- December 13, 2024 update (en Español)
- December 6, 2024 update (en Español)
- November 29, 2024 update (en Español)
- November 22, 2024 update (en Español)
- November 15, 2024 update (en Español)
- November 8, 2024 update
- November 1, 2024 update (en Español)
- October 25, 2024 update (en Español)
- October 18, 2024 update (en Español)
- October 11, 2024 update (en Español)
- October 4, 2024 update (en Español)
- September 28, 2024 update (en Español)
- September 20, 2024 update (en Español)
- September 13, 2024 update (en Español)
- September 6, 2024 update (en Español)
- August 30, 2024 update
- August 23, 2024 update (en Español)
- August 16, 2024 update (en Español)
- August 9, 2024 update (en Español)
- August 2, 2024 update (en Español)
- July 26, 2024 update (en Español)
- July 19, 2024 update (en Español)
- July 12, 2024 update (en Español)
- July 5, 2024 update (en Español)
- June 28, 2024 update (en Español)
- June 21, 2024 update (en Español)
- June 14, 2024 update (en Español)
- June 7, 2024 update
- May 31, 2024 update (en Español)
- May 24, 2024 update (en Español)
- May 17, 2024 update (en Español)
- May 10, 2024 update (en Español)
- May 3, 2024 update (en Español)
- April 26, 2024 update (en Español)
- April 19, 2024 update (en Español)
- April 12, 2024 update (en Español)
- April 5, 2024 update (en Español)
- March 29, 2024 update (en Español)
- March 22, 2024 update (en Español)
- March 15, 2024 update (en Español)
- March 8, 2024 update (en Español)
- March 1, 2024 update (en Español)
- February 23, 2024 update (en Español)
- February 16, 2024 update (en Español)
- February 9, 2024 update (en Español)
- February 2, 2024 update (en Español)
Weekly monitoring probe and well installation update in accordance with Milestone 4-2:
- January 15, 2025 update
- January 8, 2025 update
- December 31, 2024 update (en Español)
- December 24, 2024 update (en Español)
- December 18, 2024 update (en Español)
- December 11, 2024 update (en Español)
- December 4, 2024 update (en Español)
- November 27, 2024 update (en Español)
- November 20, 2024 update (en Español)
- November 13, 2024 update
- November 6, 2024 update (en Español)
- October 30, 2024 update (en Español)
- October 23, 2024 update (en Español)
- October 16, 2024 update (en Español)
- October 9, 2024 update (en Español)
- October 2, 2024 update (en Español)
- September 25, 2024 update (en Español)
- September 18, 2024 update (en Español)
- September 11, 2024 update (en Español)
- September 5, 2024 update (en Español)
- August 28, 2024 update (en Español)
- August 21, 2024 update (en Español)
- August 14, 2024 update (en Español)
- August 7, 2024 update (en Español)
- July 31, 2024 update (en Español)
- July 24, 2024 update (en Español)
- July 17, 2024 update (en Español)
- July 10, 2024 update (en Español)
- July 3, 2024 update (en Español)
- June 26, 2024 update (en Español)
- June 19, 2024 update (en Español)
- June 12, 2024 update
- June 5, 2024 update (en Español)
- May 29, 2024 update (en Español)
- May 22, 2024 update (en Español)
- May 16, 2024 update (en Español)
Monthly reports pursuant to Milestones 1A-3 and 5 of the LEA’s June 6, 2024 Compliance Order and the LEA letter dated July 30, 2024:
- December 2024
- November 2024 (en Español)
- October 2024 (en Español)
- September 2024 (en Español)
- August 2024 (en Español)
Additional LEA Correspondence
- December 24, 2024 letter notifying the LEA of the changed temperature monitoring probe locations (en Español)
- December 3, 2024 letter requesting an extension of Milestone 2A-1 of the LEA Compliance Order (en Español)
- November 27, 2024 response to the LEA’s requests for additional information on October 2024 Milestone 1A-3 and 5 monthly report (en Español)
- November 26, 2024 submittal of a revised Soil Reaction Break/Barrier Plan (en Español)
- November 26, 2024 response to the LEA’s September 24, 2024 letter requesting a revised Soil Reaction Break/Barrier Plan (en Español)
- November 18, 2024 submittal of a proposed revised Remediation Plan and response to the LEA’s October 11, 2024 letter (en Español)
- November 12, 2024 letter responding to the LEA's September 11, 2024 letter requesting to amend Milestone 2B
- September 25, 2024 letter requesting an extension of Milestones 2A-1 and 4-4 of the LEA Compliance Order (en Español)
- September 3, 2024 response to the LEA’s July 30, 2024 Letter request regarding the June 6, 2024 Carbon Monoxide and Hydrogen Reading Summary Report pursuant to Milestone 1A-3
- August 22, 2024 submittal of updated probe and well data and Master Gas Collection and Control System Map (en Español)
- August 8, 2024 response to the LEA’s July 30, 2024 amendment to the Milestone 1B-2(C) Compliance Order (en Español)
- August 2, 2024 letter requesting an extension to the installation of the geosynthetic cover
- July 31, 2024 Landfill Gas Extraction Well Completion Report pursuant to Milestone 4-1 of the LEA’s Compliance Order (en Español)
- July 15, 2024 response to the LEA’s June 27, 2024 letter on the installation of three additional temperature monitoring probes (en Español)
- July 10, 2024 response to the LEA’s July 5, 2024 follow up questions on the status of the additional well installation (en Español)
- July 8, 2024 response to the LEA’s June 21, 2024 request regarding the scope of the geosynthetic cover pursuant to Milestone 2A-1 (formerly Mitigation Measure 2A) (en Español)
- June 6, 2024 updated carbon monoxide and hydrogen readings for all vertical gas collection wells in the reaction area and wells 200 feet outside the reaction area pursuant to directive #5 of the April 5, 2024 letter (en Español)
- June 12, 2024 response to the LEA’s May 29, 2024 letter on the installation of three additional temperature monitoring probes
- June 6, 2024 Revised Final Construction Report for the temperature monitoring probes (en Español)
- June 27, 2024 response to the LEA’s June 13, 2024 email (en Español)
- May 14, 2024 updated schedule on the installation of the geosynthetic cover(Mitigation Measure #2A) (en Español)
- May 14, 2024 proposed West Toe Drain Workplan (Mitigation Measure #2A) (en Español)
- carbon monoxide and hydrogen readings for all vertical gas collection wells in the reaction area and wells 200 feet outside the reaction area pursuant to directive #5 of the April 5, 2024 letter (en Español)
- Final Construction Report for the temperature monitoring probes in response to directive # 2 in the April 5, 2024 letter (en Español)
- April 19, 2024 updated installation schedule for the geosynthetic cover
- April 16, 2024 second revised written plan for tracking cover issues (Mitigation Measure #2B) (en Español)
- April 16, 2024 request for extension on the installation of the temperature monitoring probes (Mitigation Measure #1B) (en Español)
- April 12, 2024 response to the LEA’s April 5, 2024 letter on Mitigation Measure #1B (en Español)
- Chiquita’s March 28, 2024 response to the LEA’s March 20, 2024 letter on Mitigation Measure # 1B (en Español)
- submission of telemetry specifications (en Español)
- March 4, 2024 update on Mitigation Measure #s 1B and 2A (en Español)
- February 29, 2024 update on Mitigation Measure #2 1B and 2A (en Español)
- slope stability analysis submitted on February 22, 2024 (en Español)
- LEA’s March 22, 2024 response and request for additional analysis
- Chiquita’s January 23, 2024 response to Mitigation Measure #2A (en Español)
- January 17, 2024 response to Mitigation Measure #1B (en Español)
- January 2, 2024 response to Mitigation Measure #1B (en Español)
- December 29, 2023 response to Mitigation Measure #2A (en Español)
- December 21, 2023 response to Mitigation Measure #2B (en Español)
- December 20, 2023 response to Mitigation Measure #1B (en Español)
- December 19, 2023 response to Mitigation Measure #2A (en Español) and the Local Enforcement Agency’s December 14, 2023 letter
- December 14, 2023 response to Mitigation Measure 3 (view en Español)
- December 8, 2023 response to Mitigation Measure #2A (en Español)
- December 6, 2023 response to Mitigation Measure #2B (en Español)
- December 7, 2023 response (view en Español) to the Local Enforcement Agency’s November 21, 2023 letter
- October 20, 2023 response (view en Español) to the Local Enforcement Agency’s October 17 letter
Los Angeles County Public Works
Odor Mitigation Reports Required by the Landfill’s Conditional Use Permit:
- December 24, 2024 Supplemental CUP Condition 69 Report (en Español)
- November 22, 2024 Supplemental CUP Condition 69 Report (en Español)
- October 25, 2024 Supplemental CUP Condition 69 Report (en Español)
- September 27, 2024 Supplemental CUP Condition 69 Report (en Español)
- August 29, 2024 Supplemental CUP Condition 69 Report (en Español)
- July 26, 2024 Supplemental CUP Condition 69 Report (en Español)
- June 28, 2024 Supplemental CUP Condition 69 Report (en Español)
- May 24, 2024 Supplemental CUP Condition 69 Report (en Español)
- April 26, 2024 Supplemental CUP Condition 69 Report (en Español)
- March 27, 2024 Supplemental CUP Condition 69 Report (en Español)
- February 23, 2024 Supplemental CUP Condition 69 Report (en Español)
- January 26, 2024 Supplemental CUP Condition 69 Report (en Español)
- December 28, 2023 Supplemental CUP Condition 69 Report (en Español)
- November 22, 2023 Supplemental CUP Condition 69 Report (en Español)
- October 24, 2023 Supplemental CUP Condition 69 Report (en Español)
- September 22, 2023 Supplemental CUP Condition 69 Report (en Español)
- August 23, 2023 Supplemental CUP Condition 69 Report (en Español)
- July 27, 2023 report submitted pursuant to Condition 69 of Chiquita’s Conditional Use Permit (en Español)
- Chiquita’s October 5, October 12 (en Español), October 19 (en Español), October 31 (en Español) and December 5 responses to Public Works’ September 20 letter
- Chiquita’s August 18, 2023 response (en Español) to the Department of Public Works’ August 3 letter
Los Angeles County Department of Public Health
- Chiquita’s August 15, 2023 response (en Español) to the Department of Public Health’s August 8 letter
- Chiquita’s August 1, 2023 response (en Español) to the public health notice issued by the Department of Public Health on July 26, 2023
Los Angeles Regional Water Quality Control Board
- January 15, 2025 Fourth Quarter Groundwater Monitoring Report to the Water Board
- January 15, 2025 Liner Integrity Memorandum for the Fourth Quarter Liner Integrity Report to the Water Board
- December 30, 2024 report to the Water Board on the December 24, 2024 leachate seep (en Español)
- December 27, 2024 report to the Water Board on the December 22, 2024 leachate seep (en Español)
- December 17, 2024 report to the Water Board on the December 10, 2024 leachate spill (en Español)
- December 11, 2024 response to the Water Board regarding Chiquita’s request for reconsideration of the Water Board’s September 25, 2024 denial of authorization to place waste in Cell 8B (en Español)
- December 3, 2024 report to the Water Board on the November 26, 2024 leachate spill (en Español)
- October 30, 2024 report to the Water Board on the October 23, 2024 leachate spill (en Español)
- October 29, 2024 report to the Water Board on the October 21, 2024 leachate seep (en Español) and correction (en Español)
- October 24, 2024 report to the Water Board on the October 17, 2024 leachate seep (en Español)
- October 24, 2024 report to the Water Board on the October 17, 2024 leachate spill (en Español)
- October 15, 2024 Third Quarter Groundwater Monitoring Report to the Water Board (en Español)
- October 15, 2024 Liner Integrity Memorandum for the Third Quarter Liner Integrity Report to the Water Board (en Español)
- October 8, 2024 report to the Water Board on the October 1, 2024 leachate seep (en Español)
- October 3, 2024 report to the Water Board on the September 28, 2024 leachate seep (en Español)
- October 3, 2024 report to the Water Board on the September 27, 2024 leachate seep (en Español)
- October 3, 2024 report to the Water Board on the September 26, 2024 leachate seep (en Español)
- September 13, 2024 report to the Water Board on the September 9 leachate seep (en Español)
- September 13, 2024 report to the Water Board on the September 8 leachate spill (en Español)
- September 13, 2024 report to the Water Board on the September 8 leachate seep (en Español)
- September 10, 2024 Letter to the Water Board regarding sampling and installation of wells DW-30, DW-31, and FP-01. (en Español)
- August 27, 2024 leachate seep report submitted to the Water Board pursuant to MRP No. CI-6231 Section B.3.a. (en Español)
- August 23, 2024 revised Master Development Plan Stability Analyses for Cell 8B. (en Español)
- August 21, 2024 Letter to the Water Board re the revised workplan, extension request and updates for sampling of wells DW-30, DW-31, and FP-01. (en Español)
- July 26, 2024 response to the Water Board’s June 27, 2024 Notice of Violation (en Español)
- Attachments to Chiquita's July 26, 2024 response
- July 19, 2024 Liner Integrity Memorandum for the First Quarter Liner Integrity Report to the Water Board (en Español)
- July 18, 2024 report to the Water Board on the July 12, 2024 leachate seep (en Español)
- July 15, 2024 letter to the Water Board (en Español) enclosing the first quarterly groundwater monitoring and liner integrity reports pursuant to paragraphs 1(d) and (f) of the March 20, 2024 Investigative Order and an initial response to the Water Board’s June 27, 2024 Notice of Violation. The attachments to this letter are below:
- July 12, 2024 report to the Water Board on the July 6, 2024 leachate seep (en Español)
- July 12, 2024 report to the Water Board on the July 5, 2024 leachate seep (en Español)
- June 28, 2024 letter to the Water Board regarding the Water Board’s June 6, 2024 denial of the final construction report for Cell 8B (en Español)
- June 26, 2024 report to the Water Board on the June 19, 2024 leachate seep (en Español)
- June 17, 2024 report to the Water Board on the June 10, 2024 leachate seep (en Español)
- May 21, 2024 report to the Water Board on the May 14, 2024 leachate seep
- May 17, 2024 report to the Water Board on the May 13, 2024 leachate seep
- May 16, 2024 response to the Water Board's April 9 NOV (en Español)
- May 14, 2024 report to the Water Board on the May 7, 2024 leachate seep (en Español)
- May 13, 2024 30-Day Storm Report to the Water Board in response to the March 20, 2024 Investigative Order (en Español)
- May 9, 2024 report to the Water Board on the May 2, 2024 leachate seep (en Español)
- May 8, 2024 report to the Water Board on the May 1, 2024 leachate seep (en Español)
- April 30, 2024 report to the Water Board on the April 23, 2024 leachate seep (en Español)
- April 29, 2024 30-Day Storm Report to the Water Board in response to the March 20, 2024 Investigative Order (en Español)
- April 29, 2024 response to the Water board’s March 28 NOV (en Español)
- April 22, 2024 response to the Water Board’s March 20, 2024 Investigative Order (en Español)
- March 15, 2024 report to the Water Board on the March 8, 2024 leachate seep (en Español)
- March 7, 2024 report to the Water Board on the March 4, 2024 leachate seep
- March 7, 2024 report to the Water Board on the March 3, 2024 leachate seep
- March 7, 2024 report to the Water Board on the March 1, 2024 leachate seep
- March 7, 2024 report to the Water Board on the February 29, 2024 leachate seep in Grid 145
- March 7, 2024 report to the Water Board on the February 29, 2024 leachate seep in Grid 207
- February 28, 2024 report to the Water Board on the February 21, 2024 leachate seep (en Español)
- February 27, 2024 report to the Water Board on the February 20, 2024 leachate seep (en Español)
- February 26, 2024 report to the Water Board on the February 19, 2024 leachate seep (en Español)
- February 20, 2024 report to the Water Board responding to the November 22, 2023 NOV (en Español)
- February 14, 2024 report to the Water Board on the February 7, 2024 leachate seep (en Español)
- February 12, 2024 report to the Water Board on the February 5, 2024 leachate seep (en Español)
- February 8, 2024 report to the Water Board on the February 3, 2024 leachate seep (en Español)
- January 26, 2024 report to the Water Board on the January 21, 2024 leachate seep (en Español)
- January 22, 2024 report to the Water Board on the January 15, 2024 leachate seep (en Español)
- January 15, 2024 report to the Water Board on the January 8, 2024 leachate seep (en Español)
- December 29, 2023 report to the Water Board on the December 22, 2023 leachate seep (en Español)
- December 22, 2023 response(en Español) to the Los Angeles Regional Water Quality Control Board notice of violation issued on November 22, 2023
Department of Toxic Substances Control
- April 12, 2024 additional response to DTSC’s March 29, 2024 Summary of Violations (en Español)
- April 1, 2024 initial response to DTSC’s March 29, 2024 Summary of Violations (en Español)
- March 29, 2024 response to DTSC’s request for information (en Español)
- March 19, 2024 response to DTSC’s request for information (en Español)
- March 15, 2024 response to the February 15, 2024 DTSC Summary of Violations (en Español)
- March 8, 2024 response to DTSC’s request for information (en Español)
- February 12, 2024 response to DTSC (en Español)
- Supplemental and revised February 2, 2024 response to DTSC (en Español)
- January 26, 2024 response to the Department of Toxic Substances Control request for information (en Español)
U.S. Environmental Protection Agency
- Cover Installation Plan the EPA UAO's letter of approval
- Environmental Protection Agency’s June 4, 2024 Finding of Violation to Chiquita under Section 113(a) of the Clean Air Act
- Slope Stability Analysis Workplan and the EPA UAO’s letter of approval (en Español)
- Updated Air Monitoring Workplan and the EPA UAO’s letter of approval (en Español)
Other Regulators
- July 31, 2024 Compliance Plan required by the Department of Regional Planning’s notice of violation issued on July 1, 2023
- Chiquita’s September 15, 2023 response (en Español) to the Department of Regional Planning notice of violation issued on August 18, 2023
- November 17, 2023 extension request and status update (en Español)
- Chiquita’s September 6, 2023 response (en Español) to County Counsel’s September 1 letter
Air Quality
Access Chiquita's Air Monitoring Program data here.
Air quality monitoring required under Condition 68 of the CUP is ongoing. Air monitoring equipment is operational at all five on-site locations at the landfill and all seven off-site locations in the surrounding community. Further information and the consultant’s presentations to the Community Advisory Committee on the air monitoring program are available on the Community Advisory Committee webpage.
Consultant Reports Submitted to the CAC, TAC, or Any Government Agency as required under Condition 68 of Chiquita’s CUP:
Quarterly or Annual Reports Submitted to the Los Angeles Department of Public Health or South Coast AQMD as required under Condition 68 of Chiquita’s CUP:
- Third Quarter 2024 Community Air Monitoring Report (en Español)
- Second Quarter 2024 Community Air Monitoring Report (en Español)
- First Quarter 2024 Community Air Monitoring Report (en Español)
- Annual 2023 Community Air Monitoring Report (en Español)
- Fourth Quarter 2023 Community Air Monitoring Report (en Español)
- Third Quarter 2023 Community Air Monitoring Report (en Español)
- Second Quarter 2023 Community Air Monitoring Report (en Español)
- First Quarter 2023 Community Air Monitoring Report (en Español)
- Annual 2022 Community Air Monitoring Report (en Español)
- Third Quarter 2022 Community Air Monitoring Report (en Español)
- Fourth Quarter 2022 Community Air Monitoring Report (en Español)
Monthly Data and Quarterly Summary Reports Submitted to the Los Angeles Department of Public Health
- November 2024 monthly data report (en Español)
- Third Quarter 2024 report (en Español)
- October 2024 monthly data report (en Español)
- September 2024 monthly data report (en Español)
- Second Quarter 2024 report (en Español)
- August 2024 monthly data report (en Español)
- July 2024 monthly data report (en Español)
- June 2024 monthly data report (en Español)
- May 2024 monthly data report (en Español)
- April 2024 monthly report Part 1 and Part 2
- First Quarter 2024 report (en Español)
- March 2024 monthly data report (en Español)
- February 2024 monthly data report (en Español)
- January 2024 monthly data report (en Español)
- Fourth Quarter 2023 report (en Español)
- December 2023 monthly data report (en Español)
- November 2023 monthly data report (en Español)
- October 2023 monthly data report (en Español)
- CTEH’s analysis of the August through October 2023 data (en Español)
- Third Quarter 2023 quarterly report (en Español)
- September 2023 monthly data report (en Español)
- CTEH's analysis of the August and September 2023 data (en Español)
- August 2023 monthly data report (en Español)
- CTEH's analysis of the August 2023 data (en Español)
- Chiquita’s December 22, 2023 report on the feasibility of conducting continuous monitoring for DMS and benzene, toluene, ethylbenzene, and total xylenes (BTEX) submitted to the Department of Public Health (en Español)
- South Coast AQMD Rule 1150.1 monitoring reports dating back to 2018 are available on the Landfill Reports section of Chiquita’s website
Upcoming Public Meetings
Chiquita will host the following Community Information Meetings to discuss current updates and odor mitigation efforts at the Landfill.
Next Community Information Meeting - February 6, 2025 at 6:00 PM
Virtual - Join Zoom meeting
Mobile - +1 669 900 6833 US
Public comments will be received at these meetings.
Webinar ID: 921 8583 8562
Previous Community Information Meeting Materials
- January 9, 2025 - View - recording | presentation
- December 12, 2024 - View - recording | presentation
- November 7, 2024 - View - recording | presentation
- October 10, 2024 - View - recording | presentation
- September 12, 2024 - View - recording | presentation
- August 8, 2024 - View - recording | presentation
- July 11, 2024 - View - recording | presentation
- June 6, 2024 - View - recording | presentation
- May 2, 2024 - View - recording | presentation
- April 4, 2024 - View - recording | presentation
- March 7, 2024 - View - recording | presentation
- February 15, 2024 - View - recording | presentation
- January 11, 2024 - View - presentation | Due to technical difficulties, the recording from the Community Information Meeting is not available. We apologize for the inconvenience.
- December 7, 2023 - View - recording | presentation
- November 9, 2023 - View - recording | presentation
- October 5, 2023 - View - recording | presentation
- September 14, 2023 - View - recording | presentation
- August 10, 2023 - View - recording | presentation
Community Advisory Committee Meeting
Community Advisory Committee Meetings are held on the 2nd Tuesday of every month. Meetings start at 6:00 pm.
The Chiquita Canyon Landfill Community Advisory Committee (CAC) was established in accordance with Conditional Use Permit No. 2004-00042, which was approved by the County of Los Angeles (County) Board of Supervisors (Board) on July 25, 2017. The CAC serves as an advisory body to the Board, Regional Planning Commission (Commission), and County Staff on issues relating to the Landfill, and as a conduit for the community to communicate with the Commission and other regulatory agencies on an ongoing basis regarding issues involving the development and operation of the Landfill. Chiquita representatives attend the meetings of the CAC to provide regular, and timely updates and reports regarding landfill operations as a means to maintain an open line of communications with local leaders and residents.
Next CAC meeting - Tuesday, February 11, 2025 at 6:00 PM.
In person - Castaic Library (27971 Sloan Canyon Rd, Castaic, CA 91384).
A registration link to attend the meeting will be provided once it becomes available.
Public comments will be received at these meetings.
More information can be found on the CAC website.
Technical Advisory Committee Meeting
The Chiquita Canyon Landfill Technical Advisory Committee (TAC) consists of County Planning, Department of Public Health, Department of Public Works, and the Forester. The TAC was established for the purpose of reviewing, coordinating, and certifying the satisfactory implementation and/or completion of the plans, permits, and/or agreements required and/or authorized by the Landfill’s Conditional Use Permit, including the implementation and/or completion of the Conditions of Approval, the Implementation and Monitoring Program, and the Mitigation Monitoring and Reporting Program.
Next TAC meeting – TBD
Meeting information will be posted here when it is made available.
More information can be found on the TAC website.
Castaic Area Town Council Meeting
Town hall meetings are held on the 3rd Wednesday of every month. Meetings start at 6:30 pm, commencing by 6:45 pm, and are usually completed by 9 pm.
Next CATC meeting – February 19, 2025
You can join the Zoom Meeting using the following link: https://us02web.zoom.us/j/89674085265...
Meeting ID: 896 7408 5265
Passcode: 211269.
Alternatively, you can dial in at +1 669 900 9128.
Public comments will be received at these meetings.
South Coast AQMD Hearing
A status update and modification hearing on the Stipulated Order for Abatement will be held before the South Coast AQMD Hearing Board on February 5 and 6, 2025, at the SCAQMD Headquarters in Diamond Bar. Virtual public comments will be received at the hearing.
Virtual - Join via Zoom - Meeting ID: 914 2934 2608o
Call - 669 900 6833
One tap mobile
FAQ + Useful links
Use the below accordions to view answers to FAQ (Frequently Asked Questions) from the community. Please also see the useful links below that will take you to articles off of this site.
Chiquita Canyon: An Update on State’s Response
The Signal, by Pilar Schiavo - April 2, 2024
All Hands Needed on Chiquita
The Signal, Becki Robb - April 9, 2024
Castaic school district, landfill working on air quality mitigation
The Signal, Tyler Wainfeld - April 12, 2024
Why is Chiquita Canyon, LLC (Chiquita) not taking the reaction and its impacts on the community, or the community’s complaints, seriously?
Chiquita takes very seriously its role in the safe operation of the Chiquita Canyon Landfill (Landfill) and in open, real-time communication with the local community and Chiquita’s regulators. Chiquita and its many consultants and experts have been working around the clock over the past several months to implement a multitude of mitigation measures to address and stop the landfill reaction and any related impacts. Chiquita has implemented an incident command system to better restructure its response to the reaction and ensure continued cooperation with Chiquita’s regulators. Chiquita provides regular updates on the implementation of its mitigation measures and other updates concerning the landfill to both its regulators and to the public. Chiquita continues to work cooperatively with the U.S. Environmental Protection Agency (EPA) and all of its regulators to resolve the situation as quickly as possible.
Chiquita cares about the community and takes seriously the community’s complaints. Chiquita has established a new Community Relief Program to assist with offsetting costs associated with odor mitigation. Through this program, residents of Val Verde, Live Oak, Hasley Hills, Hillcrest Parkway, Hasley Canyon, and Stevenson Ranch are able to request funding that can be used for expenses associated with odor mitigation, including temporary relocation, home hardening, and increased utility bills. Applicants may also request an air filtration device or replacement air filters. Funding will be available on a monthly basis. If you are interested in applying for this program, visit https://www.chiquitalandfillcommunityrelief.com/ to apply. Please note that submission of the application form and receipt of compensation does not constitute a release of any legal claims you may have against the Landfill or any related entities and does not constitute a waiver of any additional damages to which you may be entitled.
There have been many complaints from the community of eye irritation, respiratory symptoms, and skin issues. Why has Chiquita continued to say there are no health impacts facing the local community?
Chiquita fully recognizes that neighboring communities are suffering odor-related impacts as a result of the reaction. Recognizing these impacts, Chiquita has committed and is currently working to provide assistance to those affected by odors from the Landfill. The current data and evaluation by experts, including an independent health risk evaluation conducted at the direction of the Los Angeles County Department of Public Health, show that there are no anticipated long-term health impacts from these odors. However, the study by the Department of Public Health states, and Chiquita recognizes, that odors may cause short-term health impacts or may otherwise affect quality of life.
Pursuant to a Stipulated Order for Abatement with South Coast AQMD, Chiquita was required to have prepared by a third party an analysis of potential health impacts and an assessment of potential odor impacts. In compliance with this requirement, toxicologists with CTEH prepared a Health Impacts Report and toxicologists with Intertox prepared an Odor Impacts Assessment Report. An easy-to-read summary of the reports is attached immediately below, along with copies of the reports and supporting information:
- Public Summary of the Health Impacts and Odor Impacts Assessment Reports (en Español)
- August 1, 2024 CTEH Health Impacts Report (en Español)
- August 1, 2024 Intertox Odor Impacts Assessment Report (en Español):
Why does the landfill continue to ignore the local community’s pleas for assistance regarding the odor?
Chiquita has and continues to address the community’s requests for assistance. Chiquita previously released $3.5 million in funding to Los Angeles County to be used to fund environmental, educational, and quality of life programs, or to fund regional public facilities that serve the Val Verde, Castaic, and other unincorporated areas of the County surrounding the Landfill. Los Angeles County used $2.5 million of those funds to establish the County’s Utility Relief Grant Program. This new program is run by Chiquita and has a wider scope than the County’s program, offering payments for more neighborhoods and for additional expenses.
Chiquita has also distributed over one thousand air filtration devices to the community and continues to make the devices as well as replacement air filters available to the community. For more information on each of these programs, please visit the following webpage: https://chiquitacanyon.com/odor-mitigation/.
Evidence of the landfill reaction dates back to May 2022, resulting in thousands of odor complaints in 2023 and 2024 thus far, as well as multiple regulatory actions in 2023 and 2024. Why has Chiquita done nothing about this?
In cooperation with its many regulators, Chiquita has implemented a multitude of mitigation measures to better understand and address and stop the landfill reaction. Chiquita started implementing many of these mitigation measures voluntarily when the reaction first began and is now implementing these measures, as well as many more, as required by and in coordination with its regulators. More information on these mitigation measures and status updates on the implementation of these measures is available at the following webpage: https://chiquitacanyon.com/odor-mitigation/. Chiquita continues to work cooperatively with the EPA and all of its regulators to resolve the situation as quickly as possible.
Why isn’t Chiquita being transparent about current issues at the Landfill?
Chiquita takes very seriously its role in the safe operation of the Landfill and in open, real-time communication with the local community and Chiquita’s regulators. Chiquita consistently participates in and answers questions during multiple public community meetings that occur each month. Chiquita also updates its website on at least a weekly basis with information about current issues at the Landfill and the multitude of mitigation measures and activities that Chiquita is conducting and data that Chiquita is collecting. Please see the following webpage for more information: https://chiquitacanyon.com/odor-mitigation/.
Is there a fire at the Landfill?
No, there is no fire at the Landfill. The Landfill is experiencing an elevated temperature landfill (ETLF) event, or a “reaction” – a chemical reaction occurring deep within an old portion of the Landfill, which has resulted in elevated temperatures and increased generation of landfill gas and leachate (liquids produced by a landfill). Things such as increased leachate production would not occur with a fire—the amount of leachate produced by the Landfill has increased tenfold since the ETLF event.
Is Chiquita discharging hazardous waste into the environment? Is the landfill leachate presenting a serious and dangerous situation at the Landfill?
Chiquita has significantly increased the frequency of its leachate sampling in order to determine when leachate exceeds regulatory levels and has retained a third-party consultant to assist in the proper characterization, management, treatment, and disposal of potentially hazardous leachate. Only leachate tanks that have been confirmed non-hazardous and approved by the off-site non-hazardous treatment and disposal facilities are shipped offsite to those facilities.
All other leachate is handled as if it were hazardous waste and shipped to permitted hazardous waste treatment and disposal facilities. Chiquita has also begun treating its leachate. If post-treatment confirmatory sampling shows that the leachate is below regulatory levels, Chiquita sends the non-hazardous leachate to its non-hazardous treatment and disposal facilities once approval by those facilities has been received. If post-treatment confirmatory sampling shows that the leachate is still above regulatory levels, Chiquita handles the leachate as if it were hazardous and only ships it to permitted treatment and disposal facilities.
Chiquita is also testing its onsite sedimentation basin on a regular basis, at least semiannually and prior to discharge, to determine whether stormwater mixed with leachate made it to the basin during or after a rain event. Any discharges to waterways outside of the Landfill are through the sedimentation basin. Chiquita is waiting test results from a recent rain event, but has not yet received any indication that leachate seepage that reached the stormwater channel made it to the sedimentation basin.
Chiquita is also working cooperatively with its County, state, and federal regulators, many of which are regularly coming onsite to assess the management of this leachate, and is making sure that any risks related to the management and handling of potentially hazardous leachate do not come to fruition.
There are reports that the odor is going to continue for as long as the ETLF event is happening, and ETLF events can last for years. Is this true?
As Chiquita has discussed at several of the community meetings it hosts and attends, the ETLF conditions may continue for years, but once Chiquita is able to fully implement some of the mitigation measures that are currently in progress, it believes that it will be able to mitigate or eliminate odor impacts in the shorter term. This has been the experience at several other of the 10 to 15 landfills across the country that have experienced ETLF events in the majority of their waste mass.
Are these ETLF events or landfill reactions common?
No. There are hundreds of municipal solid waste landfills in North America, but there are only approximately 10 to 15 landfills with the majority of their waste mass that can be characterized as experiencing an ETLF event or landfill reaction. There are also only another 40 or so other landfills that have had a relatively limited portion of their waste mass exhibit ETLF conditions.