Alert: Landfill Gas Collection and Control Equipment Unplanned Down Time on 8/22/2026 at 11:06 pm
On Saturday, August 22, 2026, Chiquita experienced unplanned downtime of Flare 2 at approximately 11:06 pm due to flame failure. Flare 2 was restarted on August 23, 2026 at 6:09 am, but then experienced another downtime at 7:45 am. Chiquita anticipates that Flare 2 will be restarted on August 23, 2026, by 10:00am. This downtime is anticipated to last for a total of up to 9 hours and 18 minutes. Due to this downtime, there may be a possibility of increased odors in the community during the indicated time period.
Under Condition 81 of the Modified Stipulated Order for Abatement in Case No. 6177-4, Chiquita Canyon, LLC (Chiquita) is required to notify the community (i) if any individual control device has downtime which is anticipated to last 30 minutes or more or once any downtime for an individual control device reaches 30 minutes of downtime or (ii) if the downtime of any combination of landfill gas collection equipment results or is planned to result in a reduction of gas flow to control devices by 10% or more and the downtime is anticipated to last 30 minutes or more or once any downtime for such devices reach 30 minutes of downtime. Pursuant to Condition 81, Chiquita is also required to notify the community once the gas collection and control equipment has resumed operation.
Chiquita continues to work to diligently comply with regulator orders.