Alert: Landfill Gas Collection and Control Equipment Unplanned Down Time on 11/14/2026 at 6:04pm; Resumed Operation on 11/15/2026 by 11:45am
On Saturday, November 14, 2026, Chiquita experienced unplanned downtime of Flare 2 at approximately 6:04pm due to flame failure. Flare 2 resumed operation on November 15, 2026, at approximately 6:05am, but experienced two additional unplanned downtimes. The first began at approximately 7:12am due to low temperature, with operation resuming at 9:58am. The second began at approximately 10:51am due to flame failure, with operation resuming at 11:45am.
Under Condition 81 of the Modified Stipulated Order for Abatement in Case No. 6177-4, Chiquita Canyon, LLC (Chiquita) is required to notify the community (i) if any individual control device has downtime which is anticipated to last 30 minutes or more or once any downtime for an individual control device reaches 30 minutes of downtime or (ii) if the downtime of any combination of landfill gas collection equipment results or is planned to result in a reduction of gas flow to control devices by 10% or more and the downtime is anticipated to last 30 minutes or more or once any downtime for such devices reach 30 minutes of downtime. Pursuant to Condition 81, Chiquita is also required to notify the community once the gas collection and control equipment has resumed operation.
Chiquita continues to work to diligently comply with regulator orders.